Working around an Obstruction with Modular Wall Panels

Modular building with existing building column in the way

Looking to expand your modular office, but that I-beam is in the way of the wall panels?

One of the greatest advantages of using modular wall panels for your in-plant offices is their ability to easily change and grow as your needs change.  Back in 2010, we provided a customer with a 20’x12’ modular in-plant office with an internal wall, splitting the space into two separate offices.  A few years later they decided to rearrange the wall panels, taking out the dividing wall and creating one large office space.  Earlier this year, the customer contacted us again looking to further expand upon the room, adding an additional 16’ to the system.  This is an easy modification to make.  Typically you would just disassemble the end 12’ wall, add four new 4’ modular wall panels to each of the 20’ long walls, and then close it back off with the existing 12’ end.   But this extension offered a little twist that I thought we could talk about today.  There was an I-beam right where the wall panels would go through.

Using angle and an internal steel stud to tie a modular wall panel to  an I-beam

Conceptual sketch showing how the wall panels would be secured to the I-beam

If the wall panels fall between the flanges, the most cost effective method would be to terminate the wall on both sides of the webbing and secure it to the I-beam using some 1”x6” angle and an internal stud.  This is not the cleanest method though, as the I-beam appears to cut through the wall and typically leaves a gap in the grid ceiling inside the I-beam.

conceptual model of using modular wall panels to box around an obstruction

Conceptual sketch showing how the wall panels can could be used to box out the I-beam

In this particular case the flange of the I-beam lined up with the outer sheet of gyp-board, creating an obstruction.   Because of this we simply boxed around the I-beam with wall panels, closing it off.  While this method requires a bit more in the way of materials, it allows for a very clean and uniform appearance.

modular wall panels boxing out an obstruction

The view from inside the finished modular office extension.

Mezzanine Supported Modular Office

Mezzanine with modular office above

Mezzanine supported modular office with a two-wall modular building below

Whether you’re running out of room on the plant floor or need to oversee production, mezzanines are commonly employed to support and elevate modular buildings.  Recently we received some great photos back on a project we completed last month for a mezzanine supported modular office that I thought you might like to see.  The customer was located right here in Northeast Ohio.  They were putting in a new line on the plant floor and needed to tear down some offices they had in order to make room.   There wasn’t enough space to relocate the offices elsewhere on the plant floor, so they decided to utilize some of their unused overhead space.

Side view of mezzanine and modular office.

A 9’ high mezzanine supported modular office with an 8’ high modular wall system below.

When thinking on putting in a mezzanine supported modular building, it’s important to consider just how much space is available.  Remember that with typical column spans in low seismic areas, you’ll probably lose 1’3” to 1’5” for the mezzanine itself.  If you plan on having people move through the area you will need to maintain a minimum of 7’ for clearance.  The modular building panels are typically 8’ or 9’ tall, and unless you are planning on supporting them by the structure above, you will probably want about a foot more in order to install the roof deck to the panels which helps form the membrane that holds the system together.   In this particular case the customer’s mezzanine had a clearance height of 8’7” with a 9’10” top of deck.  This provided us enough room to install a modular office above (9’ tall panels, 9’3-1/8” overall height, 8’6” clearance height) and an 8’ high (8’3-1/8” overall with a 7’6” clear ceiling height) modular wall system below.

inside modular building

Four wall modular office above the mezzanine with customer provided/ installed floor covering

While designing these mezzanine supported modular offices, we’re often asked if we can utilize the adjacent existing walls.  While this is commonly done on the main floor of a facility, unfortunately we cannot do this up on top of the mezzanine deck.   There will always be some movement and vibrations on top of an elevated structure and because of this the structure would need to be a four wall system and not tie into the adjacent walls.  In this particular care, we put in a four wall system above the mezzanine deck as well as a two wall system below the deck to create an enclosed pass way between the production floor, the front offices beyond the cinder block wall, and the production floor entrance way to the outside.

inside view of two wall modular wall system

Two wall modular wall system below the mezzanine

It took our installers 6 work days to unload and install (both mechanical and electrical) the 24’x10’ mezzanine, the 24’x10’ 4-wall modular office above, and the 9’x22’9” two wall modular wall system below, and we had yet another very happy customer.

Visiting an Old Mezzanine Supported Modular Office

mezzainine supported modular office from 1997

After almost 20 years of service this modular office is holding up great

Occasionally, I’m asked about how well our modular offices hold up over the years if they are designed so that they can be reconfigured in the future as your needs change.  Surely, after general wear and tear they will want to just order a new building anyway, no?   Well, I recently had the opportunity to visit an old customer of ours.  Over the years, we’ve provided them with a number of mezzanines, catwalks, and modular offices.  Several of the modular offices have been disassembled, modified, and reinstalled in different locations.  While there, I got an opportunity to look at this old tank platform mezzanine and A-wall 300 modular office we provided them with back in 1997.  The steel decking has started to bend up a little at the seam in a couple areas, but after almost twenty years of service the mezzanine and modular office were in excellent condition.  If the customer wanted to, it would still be a simple task to disassemble the modular office and put it up again in a new location, possibly with a few modifications.  The components are all still compatible with what we provide today.  The only design change is that the I-splines used to connect the panels in the A-wall 300 modular building system are now typically painted to match the panels as opposed to the same color as the framing on the windows and doors.  So yes, these modular buildings are built to last.