Secure Elevated Wire Partition Tool Crib

wire_tool_crib_amezz1

By Brett

This is a project we completed in NE Ohio. The customer was looking for space for a secure tool crib for maintenance storage as well as the flexibility to store product. As the product was quite heavy, we utilized the ground floor portion for storing those items and used welded galvanized fencing above to secure their maintenance department’s tool storage. The welded wire fencing was selected because of its versatility. Welded wire partition panels have a weld at each intersection of the wire. In contrast, woven wire generally has the individual wires woven and tied off or welded to a fence frame. The welded wire option is great for most jobs because it can be cut to size in the field. If you measure inaccurately, it is not the end of the world because you can trim the extra length off the panels. Likewise, if there is piping or beams running in the way it is easy enough to cut the welded wire fence panel to accommodate the obstruction, while still maintaining the wire partition panel’s integrity.

wire_tool_crib_amezz2We utilized the existing stairs and landing from the building adjacent to the new crib in an effort to cut down cost and avoid taking up more room than necessary on their plant floor. The light you see is a reminder light for the operators of the adjacent crane. It reminds them that the mezzanine and tool crib are there so that they don’t bring their load all the way back to the stop and potentially come in contact with the new structure.

wire_tool_crib_amezz3On the front side of the mezzanine, a sliding door was in place for the occasional pallets of materials for maintenance to offload and store. The customer went with a sliding door because it could be opened, a pallet of material could be set on the top of the mezzanine deck and then the sliding door could be closed while the pallet was offloaded. With a hinged gate they would have needed to pull the pallet away from the opening to close the open fall hazard, but that wasn’t going to be feasible due to the bar grating decking.

wire_tool_crib_amezz4This customer opted for a simple keyed entry on the hinge door, but they could have used a push button or key card lock with electric strike as well.

Ultimately, they were able to have secure storage for their maintenance department while keeping their product storage below, at a price that fit their budget.

 

Using Modular Building Materials to Consolidate the Engineering Department out onto the Shop Floor

Exterior view of the completed 140’ long  modular office complex

Exterior view of the completed 140’ long modular office complex

By Derick @ A-Mezz

Most commonly, when someone contacts us looking for a modular building system, they’re looking to put in something small — a 12’ x 12’ office, or a 16’ x 24’ conference room, for example. That is not always the case, though. Modular wall systems are rather versatile and can be used for much larger projects as well. These photos are all of one such project we put together for a happy customer here in Cleveland, Ohio.

Interior view down the hallway of offices as the project is being installed

Interior view down the hallway of offices as the project is being installed

The customer wanted to move their engineering department down onto the plant floor. Working alongside the customer, we came up with a design for a 140’ x 35’6” building system to go on the plant floor partially underneath a decommissioned bridge crane.   At one end we had eight 12’ x 12’ offices, and a 12’ x 14’ three walled “war room”.

Interior view of the 62’ span open area along with one of the existing bridge crane columns before it was enclosed

Interior view of the 62’ span open area along with one of the existing bridge crane columns before it was enclosed

The central section of the building was kept largely open to be set up for desk spaces. Typically, a corrugated roof deck is used to form a membrane that helps support the wall system. With the 62’ x 35’6” clear span across the room, we decided to support the wall panels and grid ceiling with a 4’ on center joist system that tied everything back to the support structure of the former bridge crane. The bridge crane columns were also boxed in with traditional construction to give the room a clean, finished appearance.

 

Finished and furnished 30’x18’ conference room.

Finished and furnished 30’x18’ conference room.

On the far end of the building we made a 30’ x 18’ conference room. The rest of the area was left connected to the main central region to be used for printers and supplies.

Primary entrance to the finished office complex .

Primary entrance to the finished office complex .

Heading into the project, one of the customer’s main concerns was to isolate their engineers from the noise of the production floor. The panels of the A-Wall 200 wall system we used offer an STC rating of 32. The internal tongue and groove connection between panels offers a uniform barrier of protection throughout the system. The areas where sound has an easier time of getting through on a wall system are usually the doors and windows. In order to help prevent this we put heavy-duty EPDM gaskets and mechanical sweeps on all the exterior doors, and used laminated glass for all the exterior windows. To further help isolate the building from the sounds of production around it, we placed a foam tape underneath the base track of the wall system, and added rolls of insulation above the acoustical grid ceiling.   After everything was put together, we had another happy customer with a quiet engineering department located right in the center of their production floor.

Using Crossover Stairs to Maneuver Around Conveyors

By Brett @ A-Mezz

We were contacted by a customer who was DSC03792looking for an easy way to circumvent a winding nest of conveyors so they would not have to serpentine around them, or worse, crawl over/under them. Some customized crossover stairs were just the ticket. We had to ensure that we did not interrupt the flow of traffic on the conveyor and next to the conveyor. Each crossover was fitted with front steps and rear steps when travel beyond the steps was necessary to let their employees have access to all four sides of the crossovers. The important thing was to increase mobility throughout the plant, while not cutting off areas they already had access to.

Each stair crossover was fitted with a 34” high DSC03794handrail on one side and had closed diamond plate treads and decking to avoid slips and falls. Each platform was 30” high. Normally we’d just make the crossover level at the top so that you have less up and down when going across the conveyors, but the customer had some obstructions we had to work around. In the foreground of the photos below you can see that there are some control panels and electrical boxes for the conveyors that we had to keep clear. As we go higher with the mid platform we have to go longer with the stairs coming from the front and rear, which would then cause the stairs to interfere with those control panels, so the customer decided that they wanted the mid platform lower.

DSC03793There was also the option to go without the mid platform and the crossover stairs coming from the front and rear of it. That was actually the original design, but their employees did not like having to walk up and down and up and down over and over – especially if they were carrying something with them. The mid platform being installed at a lower height was the compromise with regards to comfort, safety and available space.

 

The last photo in the set shows a location DSC03795where the stair crossover was actually far enough behind the conveyor control panels to do a conveyor height platform with stairs coming from the front only. All of the crossovers were installed with the ability to be removed without too much difficulty should there be any faulty equipment that needs to be removed for repair or replacement beyond the stair.